- This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
Pages
- Associated Project(s):
News-Gazette article about site selection
Associated Project(s):The News-Gazette published a follow-up article about the Solar Farm site selection. The article is online.
CAD Drawings requested for remaining 9 locations
Associated Project(s):Transportation Demand Management staff designed sketches and submitted a work order request to have formal CAD drawings made for the remaining 9 bike parking locations to be upgraded from donut hole style racks to "U" racks.
News-Gazette Article describes Solar Farm
Associated Project(s):The News-Gazette contacted SSC members and F&S to get an overview of the Solar Farm project as discussed at the BOT Audit, Budget, Finance, and Facilities sub-committee meeting. The article is online.
It was also picked up by the Chicago Tribune, Danville Area Connect, I4U, as well.
Atmospheric Sciences Building
Associated Project(s):As part of the Lighting Retrofit #5, 221 T-12 fixtures in the Atmospheric Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 34,365 hours. The simple payback for this project is 3.83 years.
Meat Sciences Laboratory
Associated Project(s):As part of the Lighting Retrofit #5, 367 T-12 fixtures in the Meat Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 66,103 hours. The simple payback for this project is 2.91 years.
F&S discussions with SSC continued
Associated Project(s):The Student Sustainability Committee met with F&S and exchanged letters and draft letters before finalizing the funding approval for the Solar Farm. Some of the related files are attached here.
Horticulture Field Laboratory
Associated Project(s):As part of the Lighting Retrofit #5, 256 T-12 fixtures in the Horticulture Field Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,187 hours. The simple payback for this project is 3.58 years.
Audit, Budget, Finance, & Facilities subcommittee forwards Solar Farm to Nov. 8 BOT agenda
Associated Project(s):The Board of Trustees Audit, Budget, Finance, and Facilities subcommittee discussed the Solar Farm project, and agreed to bring it to the Board of Trustees for approval on November 8, 2012.
SSC formal proposal submitted via email
Associated Project(s):Due to the Board of Trustees meeting schedule, the SSC has agreed to do a straw-poll about the funding of the Solar Farm project at their upcoming meeting on Oct. 26, 2012. They requested a full proposal be submitted this week, for review by committee members this coming week. The submitted proposal and associated calculations are attached here.
Free Cycling Savvy Course to be Offered October 23, 2012
Associated Project(s):On October 23, as part of the 2012 Sustainability Week, Champaign County Bikes and the University of Illinois will offer a FREE Cycling Savvy Course.
Tuesday, October 23, 2012
6:30-9:30pm
ARC Auditorium
See attached flyer for additional details.
Attached Files:Admin Info Tech Building
Associated Project(s):As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.
Team status meeting
Associated Project(s):Marcus Ricci, Stephanie Lage, Brian Deal, and Morgan Johnston met to review the status of this report. Marcus has collected a lot of data about how waste is handled on campus, and he has started to draft a summary.
Art and Design Building
Associated Project(s):As part of the Lighting Retrofit #5, 1,250 T-12 fixtures in the Art and Design Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 202,172 hours. The simple payback for this project is 3.47 years.
Sustainability Week 2012 website
Associated Project(s):see file
Attached Files:October 2012 RCx energy results
Associated Project(s):This file shows each building that has been Retrocomissioned since the program began. It includes the dates of the RCx effort, the energy reduction and related cost avoidance in utility costs.
Attached Files:Funding request submitted to SSC for FY13
Associated Project(s):In February 2012, The Bike Project submitted a funding request to SSC for $39,872. In March 2012, the SSC approved this funding.
During summer 2012, the University and The Bike Project revised their Facility Use Agreement to clarify their collaborative working relationship. The SSC sent a clarification letter regarding this update and subsequently completed a revised award letter.
payments to RSOs
Associated Project(s):From: Hanson, Claudine
Sent: Thursday, September 20, 2012 10:10 AM
To: Johnston, Morgan B; Beverage, McKenzie
Cc: Jones, John D
Subject: RE: RSO Weatherization PaymentsHere you go.
The full CFOAP for deposits into an RSO fund is 1-90xxxx-389005-307900-199000
The fund numbers are as follows:
Hong Kong Student Association 901645
Chinese Undergraduate Student Association 902108
Horticulture Club 901887
Students for Environmental Concerns 901758
American Society of Civil Engineers 901270
Let me know if you have questions.
Claudine
No concerns found for Franklin's Ground Squirrels on site
Associated Project(s):As a follow up to the EcoCAT submittal for the Solar Farm, Jim Sims worked with Dr. Edward J. Heske and Torrey W. Rodgers, from the Illinois Natural History Survey, to arrange a field survey to check for Franklin's Ground Squirrel. None were found.
Attached Files:Cost estimates requested for first 5 locations
Associated Project(s):Transportation staff submitted work order requests to have cost estimates for time and materials for the first five locations to be upgraded from donut hole bike parking to U-rack bike parking. The remaining nine locations need to have CAD drawings produced and apprroved before costs can be estimated.