  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. Composting project discussions continue

    Associated Project(s): 

    Meeting with SSC and F&S to confirm details of composting feasibility study scope.  Kevin, Matt, and Morgan worked on completing the project request form.  Kevin, Carl, and Tracy worked on detailing the transportation charges budget.  Kevin also met with Dawn Aubrey about the food waste supply.

  2. Gregory Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 426 T-12 fixtures in Gregory Hall were replaced with the more energy-effiecient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,862 hours. The simple payback for this project is -4.1 years. There are 777 T-12 fixtures in Gregory Hall remaining to be switched.

  3. David Kinley Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 858 T-12 fixtures in the David Kinley Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 84,223 hours. The simple payback for this project is -5.36 years. There are 54 fixtures that remain to be done in David Kinley Hall.

  4. Morrill Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 195 T-12 fixtures in Morrill Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 25,781 hours. The simple payback for this project is -4.45 years. There are 2,594 T-12 fixtures in Morrill Hall that remain to be switched.

  5. Lincoln Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,728 T-12 fixtures in Lincoln Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 99,886 hours. The simple payback for this project is -8.03 years.

  6. Vet Med Basic Sciences Building

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 4,248 T-12 fixtures in the Vet Med Basic Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 796,429 hours. The simple payback for this project is 0.11 years.

  7. Vet Med Large Animal Clinic

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,990 T-12 fixtures in the Vet Med Large Animal Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 320,117 hours. The simple payback for this project is 0.23 years.

  8. Vet Med Small Animal Clinic

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,928 T-12 fixtures in the Vet Med Small Animal Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 67,145 hours. The simple payback for this project is 0.83 years.

  9. Vet Med Chiller Plant

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 115 T-12 fixtures in the Vet Med Chiller Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 28,742 hours. The simple payback for this project is -0.2 years.

  10. Abbott Power Plant (partial)

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 177 T-12 fixtures in the Abbott Power Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 27,909 hours. The simple payback for this project is 0.74 years.

  11. Quick payback projects

    Associated Project(s): 

    At some point in the past, perhaps FY 09, Terry Ruprecht and the Provost’s office worked out an agreement to provide a funding source for “quick payback projects.” This meant that the payback was expected to be quick, typically in the 1-3 year range. This was a onetime funding source.  A variety of projects (10-15) have been brought forward and funded at a value of approximately 1 million dollars. These projects have included lighting retrofits, fume hood removals, chiller control upgrades, adding variable frequency drives (VFDs) to HVAC equipment,  temperature control  upgrades, and hot water control valve replacements. 

  12. Digital Computer Laboratory

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 2,793 T-12 fixtures in the Digital Computer Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 422,793 hours. The simple payback for this project is 0.23 years.

  13. Coordinated Sciences Laboratory

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,903 T-12 fixtures in the Coordinated Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 295,922 hours. The simple payback for this project is 0.78 years.

  14. Illinois State Water Survey

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,154 T-12 fixtures in nine buildings belonging to the Illinois State Water Survey were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 181,017 hours. The simple payback for this project is -2.45 years.

  15. James Hoffer, student intern, created building list file

    James provided the attached list of buildings audited by student teams in FY11.  Unfortunately, these audits were rushed and incomplete.  There were many follow up discussions about paying the student teams as originally intended, and in the end the teams were not paid.  This decision was coordinated by Mckenzie Beverage, the SSC Program Advisor, during FY12 and FY13.