Steam System Maintenance (Ongoing)

Recent Project Updates

  • 4/24/2024
    Attached is information about the senior design project presentations scheduled for next Tuesday. The project that we have been helping with is scheduled to present at 8:30 on Tuesday in 4100 LuMEB, Abbott Enerdrape System. Mike Larson
  • 10/17/2023
     Hi Mark, I am going to assign an SSC project to you as the PM to take it through design and construction.  The construction can be done through Contractor Services, so this would normally go to a Planner.  However, it will be in...

Key Objective

Description

  • The campus allocated $160,000 recurring to fund two Pipefitter FTEs to replace steam traps.  Subsequently, the Maintenance Division has added an additional two FTEs to the efforts.  
  • Ideally, steam traps will be replaced every five years, on average.
  • The SSC contributed $215,000 toward steam reduction at the Library – via PRVs, steam traps and controls.
  • The DCEO Boiler Grant is available to further support these efforts.

 

No description has been provided yet.

Project Team

  • Primary Contact:

    Morgan Johnston

Themes

Project Location(s)

This map is interactive! Click (or touch) and drag to pan; scroll (or pinch) to zoom.

View larger location(s) map